Question: TB MC Qu . 9 - 4 ( Static ) Which of the following.. Which of the following statements is true? Differences between the static

TB MC Qu.9-4(Static) Which of the following..
Which of the following statements is true?
Differences between the static planning budget and the flexible budget show what should have happened because the actual level of activity differed from what had been planned.
An unfavorable activity variance for revenue indicates that activity was less than expected when the static planning budget was developed.
The activity variance for revenue is favorable if the revenue in the flexible budget exceeds the revenue in the static planning budget.
Multiple Choice
Both statements 2 and 3 are true.Incorrect
All of the statements are true.
Only statement 1 is true.
None of the statements are true.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!