Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data
Fantastic news! We've Found the answer you've been seeking!
Question:
Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following data have been provided.
Note:
This is a level production system.
Daily demand | 150 units |
Production lead time | 0.50 day |
Safety stock | 0.25 day |
Kanban size | 50 units |
How many kanbans are needed?
________________kanbans (round your response to the nearest whole number).