Question: Telefonicax has two work centres: Work Centre A and Work Centre B The table below illustrates a number of orders to be filled this week,
Telefonicax has two work centres: Work Centre A and Work Centre B The table below illustrates a number of orders to be filled this week, each order has a setup time and a run time. Each order needs to visit each work centre to be processed to the quality required by the customer. It is essential to optimise production that setups are minimised. It is also essential to try and minimise WIP, that orders be completed as quick as possible, to ship when ready. Illustrate using a Gantt Chart, how the part production should be scheduled in both work centres