Question: Teloxy Engineering ( B ) Your manufacturing team informs you that they have found a way to increase the stre of the manufacturing run from

Teloxy Engineering (B)
Your manufacturing team informs you that they have found a way to increase the stre of the manufacturing run from 10,000 to 18,000 units, in increments of 2.000 units. However, the setup cost will be $150,000 and defects will cost the same SI20 for removal and repair.
QUESTIONS
Calculate the economic feasibility of make or buy.
Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units?
Would your answer to question 1 change if Teloxy management belleves that follow-on contracts will be forthcoming? What would happen If the probability of defects changes to 15 percent, 25 percent, 40 percent, 15 percent. and 5 percent due to learning-curve efficlencies?
 Teloxy Engineering (B) Your manufacturing team informs you that they have

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!