Terragemt, a construction company, needs to complete the construction of a skyscraper by the end of the
Fantastic news! We've Found the answer you've been seeking!
Question:
Terragemt, a construction company, needs to complete the construction of a skyscraper by the end of the next fiscal year. To meet this target, the site engineers have made plans to complete one floor each week. In this scenario, Terragemt's plan to complete one floor each week is an example of a
a
capstone goal
b
distal goal
c
proximal goal
d
passive goal