Question: Terson Technologies is working on a month - long software development project for an airline company. Time - boxing is an important Scrum principle Which

Terson Technologies is working on a month-long software development project for an airline company. Time-boxing is an important Scrum principle Which of the following pairs has been incorrectly Time-boxed according to general Scrum practice?
Daily Standup: 15 minutes
Retrospect Sprint Meeting: 8 hours
Sprint Planning Meeting: 8 hours
Sprint Review Meeting: 4 hours