The development of proposed solutions by interested contractors or by the customer's
internal project team in response to a customer's request for proposal is the
phase of the project life cycle.
a first
b second
c third
d fourth
Evaluating whether or not to go forward with the preparation of a proposal is referred
to as the
a bidnobid decision
b go for it decision
c price evaluation decision
d bid highlow decision
A proposal is a
document; it is not a
report.
a technical, management
b technical, feasibility
c selling, technical
d management, sales
In certain situations, the contractor may designate a
who coordinates
the efforts of the proposal team to ensure that a consistent, comprehensive proposal is
prepared by the due date stated in the RFP
a proposal manager
b process administrator
c process advisor
d process technician
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock