Question: ABS mall is considering building a new parking lot. The land will cost $25,000 and the construction cost of the lot is estimated to
ABS mall is considering building a new parking lot. The land will cost $25,000 and the construction cost of the lot is estimated to be $150,000. Each year costs associated with the lot are estimated to be $17,500. The income from the lot is estimated to be $18,000 the first year and increase by $3,500 each year for the twelve year expected life of the lot. Determine the B/C ratio if ABS mall uses a cost of money of 4%(Use conventional)
Step by Step Solution
3.36 Rating (149 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts