Question: Textbook Question - 2 D / 3 Given the table below ( see picture ) : If the indirect cost savings is $ 1 ,
Textbook Question D
Given the table below see picture:
If the indirect cost savings is $ per week
a Draw the network diagram
b What is the critical path?
c Provide the steps and process to crash this project
d What is the maximum time that this project can be crashed, what is the total crashing cost, and what is the new duration?
e Provide the final network diagram using the maximum crash time