Question: The _ _ _ _ _ _ _ _ _ _ blank plan must be the most flexible of the three levels of planning. These

The __________blank plan must be the most flexible of the three levels of planning. These types of plans may be amended frequently as conditions change. The __________blank plan is the least flexible and is not expected to change fundamentally for years at a time.
Multiple Choice
operational; strategic
operational; tactical
tactical; operational
strategic; operational
strategic; tactical