Question: The _ _ _ _ _ _ _ _ _ is used to assist in making project trade - offs among schedule, budget, and performance
The is used to assist in making project tradeoffs among schedule, budget, and performance objectives.aresponsibility matrixb.responsibility matrixc.project priority matrixd.work packagee.criterion matrix