Question: The _ _ _ _ _ _ _ _ _ _ _ _ _ technique is used to estimate project duration when there is a
Thetechnique is used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates. This technique uses 'probabilistic time estimates'duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations rather than one specific or discrete duration estimate.
Question options:
program evaluation and review PERT
critical path method
time series
Gantt chart
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
