Question: The _ _ _ _ _ _ _ _ _ _ _ _ _ technique is used to estimate project duration when there is a

The_____________technique is used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates. This technique uses 'probabilistic time estimates'--duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations rather than one specific or discrete duration estimate.
Question 1 options:
program evaluation and review (PERT)
critical path method
time series
Gantt chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer