Question: The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide whether to use: the critical ratio rule,

The Ace Machine Company is considering using a priority scheduling rule in its fabrication shop and must decide whether to use: the critical ratio rule, the order slack rule, the shortest operation next rule, or the slack per operation rule. The table below shows the companys current inventory and shop status.
Order Number
Total Remaining Manufacturing Time
Time Remaining until Due Date
Current Operation Processing Time
1
15
12
8
2
12
15
5
3
10
14
4
4
15
18
3
5
20
19
6
State the formula for calculating the priority index for each of the sequencing rules given previously.
Compute the scheduling priority for each order in the table, four sequencing rules.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!