Question: The activities and their durations for a software project are listed in the table below. Activity Immediate Predecessor Expected Duration ( weeks ) A -

The activities and their durations for a software project are listed in the table below.
Activity
Immediate Predecessor
Expected Duration
(weeks)
A
-
5
B
-
5
C
-
4
D
A
6
E
B
9
F
D, E
2
G
F
3
H
C
6
I
H
1
J
G
3
K
I
1
This project has been previously promised to be completed in 18 weeks. Regular employees working their regular Monday through Friday schedules are assigned to this project.
Which of the five charts below is the correct PERT chart (as an A-O-N network diagram) for this project?
a.
A:
b.
B:
c.
C:
d.
D:
e.
E:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!