Question: The activities described by the following table are given for the Howard Corporation in Kansas: Activity Time (in weeks) Immediate Predecessor(s) Activity Time (in weeks)
The activities described by the following table are given for the Howard Corporation in Kansas:
| Activity | Time (in weeks) | Immediate Predecessor(s) | Activity | Time (in weeks) | Immediate Predecessor(s) | Activity | Time (in weeks) | Immediate Predecessor(s) |
| A | 8 | D | 7 | B | G | 5 | E, F | |
| B | 8 | A | E | 10 | B | H | 7 | D |
| C | 3 | A | F | 5 | C | I | 3 | G, H |
This exercise contains only parts b and c.
Part 2
b) The activities on the critical path are:
A - C - F - G - I
A - B - E - G - I
A - B - D - H - I
.