Question: The activity time estimates ( in weeks ) are as follows: table [ [ Activity , Optimistic,Most Probable,Pessimistic ] , [ A , 3

The activity time estimates (in weeks) are as follows:
\table[[Activity,Optimistic,Most Probable,Pessimistic],[A,3.0,4.0,5.0],[B,3.0,3.5,7.0],[C,4.0,5.0,6.0],[D,2.0,3.0,4.0],[E,6.0,10.0,14.0],[F,7.5,8.5,12.5],[G,4.5,6.0,7.5],[H,5.0,6.0,13.0],[I,2.0,2.5,6.0],[J,4.0,5.0,6.0]]
a. Develop an activity schedule for this project and identify the critical path activities.
If required, round your answers to two decimal places. Enter "0" if your answer is zero.
\table[[Activity,Expected Time,Variance],[A,,],[B,,],[C,,]]
 The activity time estimates (in weeks) are as follows: \table[[Activity,Optimistic,Most Probable,Pessimistic],[A,3.0,4.0,5.0],[B,3.0,3.5,7.0],[C,4.0,5.0,6.0],[D,2.0,3.0,4.0],[E,6.0,10.0,14.0],[F,7.5,8.5,12.5],[G,4.5,6.0,7.5],[H,5.0,6.0,13.0],[I,2.0,2.5,6.0],[J,4.0,5.0,6.0]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!