Question: The activity time estimates (in weeks) are listed in the following table. (a) Develop an activity schedule for this project and identify the critical path

The activity time estimates (in weeks) are listed in the following table. (a) Develop an activity schedule for this project and identify the critical path activities. (Enter your answers as a commaseparated list.) (b) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 21 weeks? (Round your answer to four decimal places.) (c) Based solely on the critical path, what is the probability that the project will be completed so that Landon Corporation may introduce the new product within 26 weeks? (Round your answer to four decimal places.)