Question: The air pollution project discussed in the chapter has progressed over the past several weeks, and it is now the end of week 8. Lester
The air pollution project discussed in the chapter has
progressed over the past several weeks, and it is now
the end of week 8. Lester Harky would like to know
the value of the work completed, the amount of any
cost overruns or underruns for the project, and the
extent to which the project is ahead of or behind
schedule by developing a table like Table 12.8. The
revised cost figures are shown in the following table:
PERCENT OF ACTUAL
ACTIVITY COMPLETION COST ($)
A 100 20,000
B 100 36,000
C 100 26,000
D 100 44,000
E 50 25,000
F 60 15,000
G 10 5,000
H 10 1,000