The airport lounge remodeling project is well into the third month where the SPI is 1.4 and CPI is 0.8. What does this mean for the project status?
a. Over budget and behind schedule
b. Over budget and ahead of schedule
c. Ahead of schedule but under budget
d. Behind schedule and under budget