Question: The amount of delay within a task that will not delay the overall project is known as aestimated effort.free slack.opportunity cost.total slack.PreviousNextThe type of information

The amount of delay within a task that will not delay the overall project is known as aestimated effort.free slack.opportunity cost.total slack.PreviousNextThe type of information that will need to be collected during a project and who will receive this information can be found in the project planassignment.responsibility.communication.requirements,Previous