Question: The amount of time spent in a queue is _______ the time spent in the system. a. Equal to b. More than c. Less than
The amount of time spent in a queue is _______ the time spent in the system.
a. Equal to
b. More than
c. Less than
d. Double
On Black Friday, an arriving customer wanted to enter a store to purchase a new TV. She saw that there were so many people on line she decided not go in. The customer is illustrating:
Select one:
a. Reneging
b. Jockeying
c. Balking
d. Facilitating
Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the expected processing time for the activity.
Select one:
a. 3.16
b. 5.16
c. 10
d. 5.33