Question: The Analytical Hierarchy Process is used to decide among three projects that we'll call A , B , and C . The total score for

The Analytical Hierarchy Process is used to decide among three projects that we'll call A, B, and C. The total score for project A is .650, for project B is .514, and for project C is .321. Which of the following statements is BEST?
The analysis must be incorrect because project C's total score is odd.
Project A is twice as good as project C .
The analysis must be incorrect because there are two total scores that exceed 0.50.
The analysis must be incorrect because the total scores should sum to 1.00.
 The Analytical Hierarchy Process is used to decide among three projects