Question: The answer is: NPVX = $22,244.88; NPVY = $14,629.92, select Project X. I need a clear and complete working of how to get this answer.

The answer is: NPVX = $22,244.88; NPVY = $14,629.92, select Project X.
I need a clear and complete working of how to get this answer. Thanks
Below are the cash flows associated with two mutually exclusive projects: Calculate the net present value using replacement chain approach for the projects. The cost of capital is 10%.Which project should be selected? The answer is: NPVX = $22,244.88; NPVY = $14,629.92, select Project X. I need a clear and complete working of how to get this answer. Thanks