Question: ( The answers are given below each specific question at the bottom, please make sure your answers match that before submitting back to me .

(The answers are given below each specific question at the bottom, please make sure your answers match that before submitting back to me. Also make sure to show me how you got the correct answers step by step in order so I can do a problem similar! Thank you). Item A is one of the products manufactured at ABC Manufacturing.
Each order for producing the product has a cost of $80/order, regardless of the number of units ordered.
The lead time for placing the order is 1 week(s).
The inventory cost is $1/ unit/week and the on-hand inventory at the beginning of week 1 is 120 units.
The gross requirement for Item A is specified for the beginning of weeks 1 through 8 in the table that follows.
Item A
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Gross Requirement 908007004010550
On-hand Inventory
Net Requirement
Planned Order Receipt
Planned Order Release
For a "lot size using Part Period" scheduling policy, determine the total cost for the 8 week period. Assume that inventory is tracked at the beginning of the period.The number of units ordered can be a multiple of the Part Period, depending on the computed net requirement in a week.
What is total number of units held in inventory during the planning period (i.e. weeks 1 through 8)?
(The answer is 345, how did they get that)
What is number of orders during the planning period?
(The answer is 3, how did they get that)
What is the total cost of inventory and ordering for the planning period?
(The answer is 585, how did they get that)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!