Question: The Architect has issued a final certificate, but same is contested: - a . By the client who claims that certain workmanship is defective. b

The Architect has issued a final certificate, but same is contested:-
a. By the client who claims that certain workmanship is defective.
b. By the client who points out that the patent defects period has not lapsed, and has one month to run.
c. By the contractor who claims that the Quantity Surveyor re-measured the foundations measured "Provisional" in the Bills of Quantities, from drawings whereas the bill preamble indicated that the method would be via site measurement.
The Architect has issued a final certificate, but