Question: The As Late As Possible constraint is used much less frequently than others because scheduling backward from the finish date removes all slack time from
The As Late As Possible constraint is used much less frequently than others because scheduling backward from the finish date removes all slack time from tasks and makes the project schedule less flexible. This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A True option B False