Question: The average completion time ( flow time ) for the sequence developed using the FCFS rule ( = 1 1 . 7 5
The average completion time flow time for the sequence developed using the FCFS rule days round your response to two decimal places
The percentage utilization for the sequence developed using the FCFS rule enter your response as a percentage rounded to two decimal places
b Using the SPT shortest processing time decision rule for sequencing the jobs, the order is to resolve a tie, use the order in which the jobs were received:
The average tardiness job lateness for the sequence developed using the SPT rule days round your response to two decimal places
The average completion time flow time for the sequence developed using the SPT rule days round your response to two decimal places
The percentage utilization for the sequence developed using the SPT rule enter your response as a percentage rounded to two decimal places
c Using the LPT longest processing time decision rule for sequencing the jobs, the order is to resolve a tie, use the order in which the jobs were received:
The average tardiness job lateness for the sequence developed using the LPT rule days round your response to two decimal places
An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left:
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day Compute all times based on initiating work on day
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock