Question: The average demand for an item per week is 4 0 units and lead time is 2 weeks. If safety stock ( ss ) is

The average demand for an item per week is 40 units and lead time is 2 weeks. If safety stock (ss) is 20 units, then the reorder point (ROP) should be .