Question: THE AVERAGE TARDINESS(job laeness) for the sequence develope using the FCFS rul = ?? days round 2 dec. the percentage utilization for the sequence developed

THE AVERAGE TARDINESS(job laeness) for the sequence develope using the FCFS rul = ?? days round 2 dec.
the percentage utilization for the sequence developed using the FCFS rule =??%.round two dec.
using the EDD decision rule for sequencing the jobs, the order is(to resolve a tie, use the order in which the jobs were received) = a,e,b,c
the average tardiness for the sequence developed using the EDD rule= ?? days
The percentage utilization for the sequence developed using the EDD rule =??% round 2 dec
using the SPT decision rule for sequencing the jobs, the order is a,e,b,c,d
the average tardiness for the sequence developed using the SPT rule = ?? days
the percentage utilization for the sequence developed using the SPT rule = ??% round 2 dec.
using the LPT decision rule for sequencing the jobs, the order is d,c,b,e,a
the average tardiness for the sequence developed using the LPT rule = ?? days. round 2 dec.
the percentage utilization for the sequence developed using the LPT rule = ??% round 2 dec
a) Using the FCFS (first come, first served ) decision rule for sequencing the jobs, the order is (assume that jobs came in the order in which they are listed in the table): The following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrive: Sequence Job Duration (days) 40 5 Job A B C D E Due Date 325 314 315 313 312 16 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275. Assume each job starts at the beginning of the day and finishes at the end of the day (a job that begins on day 275 and takes 8 days will finish on day 282, and the next job begins in the morning of day 283). Compute all times based on initiating work on day 275Step by Step Solution
There are 3 Steps involved in it