Question: The average waiting time will increase by more than 50%. The average waiting time will increase by 50%. Question 4 0/1 pts Camille owns Crunch

The average waiting time will increase by more than 50%. The average waiting time will increase by 50%. Question 4 0/1 pts Camille owns Crunch Code, a company that provides quick programming solutions. Clients send projects to Crunch via their web page and a programmer develops the needed code as quickly as possible. Camille has five programmers, who do all of the coding. On average, a project arrives once every 4.8 hours. Each project is assigned to one programmer and that programmer takes on average 19.2 hours to complete each project. What is the average time a project has to wait before being assigned to a programmer (assume regular amount of variability, i.e., CV=1 for both arrival and service)? 26 hours 11 hours 41 hours 1 hour