Question: The backward pass in a network calculation determines: The critical path of the project. The latest times activities can be finished. The date of the

The backward pass in a network calculation determines:

The critical path of the project.

The latest times activities can be finished.

The date of the projects start if it began at the end

The earliest times activities can begin