Question: the basic block company needs to produce 4 0 0 0 boxes of blocks in a 4 0 hour work week. the process of making

the basic block company needs to produce
4
0
0
0
boxes of blocks in a
4
0
hour work week. the process of making blocks can be broken down into
6
elements. the presedence and time requirements for each element can be found in the table below:
A
(
performance time
=
0
.
1
0
min
)
B
(
precedence
=
A
)
(
performance time
=
0
.
4
0
min
)
C
(
precedence
=
A
)
(
performance time
=
0
.
5
0
min
)
D
(
performance time
=
0
.
2
0
min
)
E
(
precedence
=
C
,
D
)
(
performance time
=
0
.
6
0
min
)
F
(
precedence
=
B
,
E
)
(
performance time
=
0
.
4
0
min
)
what is the efficiency of a balanced assembly line?
a
.
9
1
.
7
%
b
.
1
0
9
.
1
%
c
.
7
3
.
3
%
d
.
6
1
.
1
%
the good answer is A: 91.7%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!