Question: The bathroom light, at work, is not working! A . Project Start B . Get permit to start 5 minutes C . Check light (
The bathroom light, at work, is not working!
A Project Start
B Get permit to start minutes
C Check light switch onoff minutes
D Have the Janitor close the bathroom minutes
E Get ladder min.
F Place ladder min
G Talk to coworker about your plans minutes
H Insure light switch is in off position min
I. Remove the bulb min
J Obtain new bulb min
K Install new bulb min
L Test by switching on min
M Talk to coworker about your plans minutes
N If it works put ladder away min
O Clean up area and properly discard old bulb min
P Return Permit to supervisor minutes
Q Project Complete
Determine what the critical path isOr is everything critical?
Can some of the steps be done sequentially? Which ones?
Can some of these activities be done concurrently? Which Ones?
Each activity has a sequence either Finish Start FSExample: You cannot place the ladder until you get it so activity E has FS relationship to activity F or Finish Finish FFWhen two activities can be completed together
a Can you identify which activities above are FS
b Can you identify activities that are FF
What is your calculation of the overall start to finish duration of this project in minutes
Define and give an example, its potential outcome and its affect on costs, using the project above, of the following items. Note: Use the depictions in the Introduction as reference.
Scope creep.
Management requests an increase to the scope.
Management wants to reduce costs.
Management wants to shorten the schedule.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock