Question: The Better Bilt Co. is fairly cautious when considering new projects and therefore analyzes each project using the most optimistic, the most realistic, and the

The Better Bilt Co. is fairly cautious when considering new projects and therefore analyzes each project using the most optimistic, the most realistic, and the most pessimistic value for all the variables. The company is conducting: Select one: a. Forecasting research. b. Sensitivity analysis. c. Scenario analysis. d. Break-even anatysis. e. Basic analysis