Question: The BOM product structure tree and gross requirements for A is given below. A 0 1 2 3 4 5 6 7 8 Gross Requirements

The BOM product structure tree and gross requirements for A is given below.

The BOM product structure tree and gross

A

0

1

2

3

4

5

6

7

8

Gross Requirements

100

250

150

If lot sizing rule is FOQ=300 and lead time=2 weeks, what would be the total projected available for B?

Question 1 options:

1000

500

700

1500

A 2 weeks C(1) 1 week D(2) 3 weeks B(1) 2 weeks 1 C(2) 1 week B(1) 2 weeks 1 C(2) 1 week