Question: The business continuity planning ( BCP ) project management and initiation phase does not involve: A . Establishing members of the BCP team B .

The business continuity planning (BCP) project management and initiation phase
does not involve:
A. Establishing members of the BCP team
B. Determining the need for automated data collection tools
C. Performing a Business Impact Analysis
D. Preparing and presenting status reports