Question: The But-for or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of delays without

  1. The "But-for" or Collapsed As-Built method for schedule delay analysis collapses the As-built schedule by removing delayed activities to identify the source of delays without any consideration of the As-planned schedule.

    True

    False

Step by Step Solution

3.32 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

False Explanation It is a technique which attempts to create an as ... View full answer