Question: The _ _ _ _ _ _ _ _ calculates the critical path and determines how long an activity can be delayed without delaying the

The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project.
Multiple Choice
concurrent pass
universal pass
forward pass
parallel pass
backward pass