Question: The _ _ _ _ _ _ _ _ calculates the critical path and determines how long an activity can be delayed without delaying the
The calculates the critical path and determines how long an activity can be delayed without delaying the project.
Multiple Choice
concurrent pass
universal pass
forward pass
parallel pass
backward pass