Question: The cash flows for two projects, C and D, are given below: Project C: Year 0: -$45,000 Year 1: $15,000 Year 2: $20,000 Year 3:
The cash flows for two projects, C and D, are given below:
Project C:
- Year 0: -$45,000
- Year 1: $15,000
- Year 2: $20,000
- Year 3: $25,000
- Year 4: $10,000
Project D:
- Year 0: -$60,000
- Year 1: $18,000
- Year 2: $22,000
- Year 3: $24,000
- Year 4: $28,000
a. Determine the NPV, IRR, and payback period for both projects, assuming a discount rate of 9 percent.
b. Discuss which project(s) should be chosen if they are independent, and which should be chosen if they are mutually exclusive.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
