Question: The CBR values, obtained from laboratory test, at 100 intervals on the centerline of a B category road (i.e. TRH4 class) section in wet region

The CBR values, obtained from laboratory test, at 100 intervals on the centerline of a B category road (i.e. TRH4 class) section in wet region (n <2) are given:
5, 7 ,6 ,7 ,7,8 ,5 ,14 ,12 ,10 ,13 ,15 ,22 ,25 ,22 ,18.
1. Delineate the subgrade into uniform sections.
2. Compute subgrade design CBR for uniform sections (show detailed calculations).
3. Draw neat, labelled sketches to show subgrade design for each delineated area.
4. Explain necessary measure to be taken if a 1.0 m long isolated rock exists on the surface at chainage 1+ 250.

Step by Step Solution

3.49 Rating (182 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

It appears that youre seeking guidance on the subgrade design for a road section based on the California Bearing Ratio CBR values obtained from labora... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!