Question: The chart below provides a general flow for turning an aircraft. Your task is to draw an Activity on Node Network ( AON ) diagram

The chart below provides a general flow for turning an aircraft. Your task is to draw an Activity on Node Network (AON) diagram and determine the critical path.
Activity Description Immediate Predecessors Time (Min)
A Aircraft stops at the gate - :00
B Jet bridge connected A :05
C Passengers deplane B :10
D Baggage offloaded A :15
E Refueling/water servicing D :20
F Gallery servicing C :15
G Cabin cleaning C :15
H Baggage loaded D :10
I Passengers boarded E, F, G :15
J Aircraft ready for departure H, I -