Question: The client asks about cycle time in a project review meeting and wants to better understand how it is defined. Whem resourcing and accelerating projects
The client asks about cycle time in a project review meeting and wants to better understand how it is defined. Whem resourcing and accelerating projects using Agile methods, which statement BEST describes cycle time?
a The forecasted number of story points a team can do in one iteration.
b The thythm of ptanning, performing, and evatuattng eath theration.
c The time from when work starts on an ltem until it is detivered.
d Muttipte team members work quickty together to solve a probilem.