Question: The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the

The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.

(a) What is the crash cost for 8 hours of time-savings?

(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?

Activity

Normal

Duration (hours)

Normal

Cost ($)

Crash

Duration (hours)

Crash

Cost (S)

Immediate

Predecessors

A21020NoneB315223AC525430BD320124CE630445CF1510C,EG735650FH1050762D,G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!