Question: The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
ActivityNormal
Duration (hours)
Normal
Cost ($)
Crash
Duration (hours)
Crash
Cost (S)
Immediate
Predecessors
A21020NoneB315223AC525430BD320124CE630445CF1510C,EG735650FH1050762D,G