Question: The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the

The client of a project has requested the project team to crash 8 hours of time. The table below
provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they
need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of
time?
Activity
Normal
Duration
(hours)
Normal
Cost ($)
Crash
Duration
(hours)
Crash
Cost (S)
Immediate
Predecessors
A 21020 None
B 315223 A
C 525430 B
D 320124 C
E 630445 C
WWW.YORKVILLEU.CA
BUSI 2113 PRODUCTION AND OPERATIONS MANAGEMENT 4
F 1510 C,E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!