Question: the company. has provided the following data to implement an activity-based costing system: Activity Cost Pools & estimated overhead cost : assembly $ 947, 100
the company. has provided the following data to implement an activity-based costing system:
Activity Cost Pools & estimated overhead cost :
assembly $ 947, 100
processing orders $ 86,130
inspection 127.946
Expected Activity:
assembly : 66,000 machine-hours
processing orders 1,800 orders
inspection 1,820 inspection-hours
The company makes 430 units of product a year, requiring a total of 690 machine-hours, 40 orders, and 10 inspection-hours per year. The products direct materials cost Is $35.82 per unit and its direct labor cost is $29.56 per unit.
The unit product cost of product under the activity-based costing system is closest to:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts