Question: The completion time of a project is expected to be 44 weeks, with a standard deviation of 2.67 weeks. What is the probability that the

The completion time of a project is expected to be 44 weeks, with a standard deviation of 2.67 weeks. What is the probability that the project will NOT be finished in 52 weeks or less? 99.865%, 100%