Question: The construction duration for the carpenter to complete the timber structure of the entire house is 1 6 weeks ( 8 hours per day )

The construction duration for the carpenter to complete the timber structure of the entire house is 16 weeks (8 hours per day). Please perform the following calculations:
a) Calculate the total cost of the timber structure of the house, given the following conditions:
The labor cost for a qualified carpenter is $120 per hour (Monday to Saturday).
Saturday's work rate is 1.5 times the normal weekday rate.
The floor dimensions of the house are 15,900mm14,500mm.
The house has four walls, as shown in Figure 1.
The cost of timber framing materials is $750 per m2.
The construction duration for the carpenter to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!