Question: The construction network plan for a unit is given in Fig 2 . Table 3 gives the man sonstruct and team size for each operation.
The construction network plan for a unit is given in Fig Table gives the man sonstruct and team size for each operation. Prepare a line of balance houses using a target rate of build houses per week. Assume a minimum buffer time of week and hours day.
a What is the overall duration of the project?
b When the house number will be started?
Fig. Network of a unit for line of balance
Table Required man hours for line of balance programming
tableOPERATIONMAN HOURS MMEN PER OPERATION QABCDEF