Question: The construction network plan for a unit is given in Fig 2 . Table 3 gives the man sonstruct and team size for each operation.

The construction network plan for a unit is given in Fig 2. Table 3 gives the man sonstruct and team size for each operation. Prepare a line of balance 40 houses using a target rate of build 4 houses per week. Assume a minimum buffer time of week and 6-hours day.
(a) What is the overall duration of the project?
(b) When the house number 30 will be started?
Fig. 2- Network of a unit for line of balance
Table 3- Required man hours for line of balance programming
\table[[OPERATION,MAN HOURS (M),MEN PER OPERATION (Q)],[A,25,2],[B,33,3],[C,45,4],[D,36,3],[E,25,2],[F,42,4]]
The construction network plan for a unit is given

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!