Question: The construction solicitation for a project was issued, and bids have been received. The estimated cost of construction for the project in the A-E requirements
The construction solicitation for a project was issued, and bids have been received. The estimated cost of construction for the project in the A-E requirements document was $2.5 million. At the bid opening, ten bids were read, and the lowest bid was $3.65 million. This project was put on the street within three months after the final design was received from the A-E firm. What should you do