Question: The contract between a subcontractor and a prime contractor provided that if the owner terminated the prime contract for any cause whatsoever at any time,
The contract between a subcontractor and a prime contractor provided that if the owner
terminated the prime contract for any cause whatsoever at any time, the subcontract would also be terminated, and the prime contractors liability would be limited to payment for work done.
The subcontractor partially performed but was not paid in accordance with the subcontract. Yet the subcontractor continued performing until it heard that the owner had terminated the prime contract. It then stopped performing, relying not on nonpayment but rather on the owners
termination having been caused by the prime contractors default.
The owners termination was based on its contractual power to terminate for its convenience. The owner terminated because it felt that the project would not be needed.
Questions:
Can the subcontractor recover from the prime contractor for work it has performed?
Can the subcontractor recover its lost profits from the prime contractor?
Would the subcontractor have been able to terminate for the prime contractors failure to make payments?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock